Custom BYD Body Kit Mold Development: From Briefing to Production
If you want to launch a body kit for a model that is not yet in our catalogue, the short answer is: mould development takes 30 to 45 days and runs through 4 technical stages — 3D scanning, CAD modelling, prototyping and production. The mould cost is a one-off, separate from production, and is amortised over the first units of the order. This guide shows how the process really works, where time tends to be lost and what has to be defined before you start.
This text is for importers, resellers and OEMs who need an exclusive product for a specific model or year.
If you are just starting out in body kit resale and are not yet familiar with the MOQ and pricing structure, see how to become a distributor.
The 4 technical stages
1. Briefing and 3D scanning (5 to 10 days)
You give us the make, model, year or year range, and which parts of the kit you want (front and rear bumper, side skirts, rear wing, rear diffuser). The technical team confirms feasibility and, if the vehicle is not in the scan database, carries out a 3D survey of the vehicle.
This step is the starting point for everything. Without a faithful scan of the car, the mould reproduces errors — and a 5 mm error on a bumper shows up as a visible gap at fitting. That is why we invest in 3D scanning even when a similar model already exists in the line: the tolerance of a derivative is not the same as that of an original product.
2. CAD modelling (7 to 12 days)
With the scan in hand, the part is modelled in CAD. Four things are defined here, and they determine the final result:
| Parameter | What is defined | Impact on the final product |
|---|---|---|
| 1. Reference line | Where the part originates: the rear line, the side line or the wheel arch | Decides whether the set looks original or "stuck on". It is the most visible parameter |
| 2. Fixing | Position of the fixing points and clips | Decides whether fitting is plug-and-play or needs adaptation |
| 3. Venting and drainage | Air outlets and drainage channels | Reduces water build-up behind the part |
| 4. Wall thickness | Distribution of the ABS thickness | Defines rigidity, weight and impact resistance |
This is the stage where it is decided whether the kit will have a paint-ready finish or will need sanding and extra finishing. Settling it here avoids rework in production.
3. Prototype and approval (10 to 15 days)
The first ABS prototype comes off. You receive photos and, when the part is complex, the option to assess a physical sample. Prototype approval is the most important moment in the project — this is where it is decided whether the set turns out as expected. Line and fixing adjustments happen at this stage, which is why it cannot be skipped.
4. Mould and series production (15 to 25 days)
With the prototype approved, the production mould is built and injection begins. From there the process is the same as any batch: injection, dimensional inspection, finishing and packaging.
What the mould cost depends on
Tooling cost varies widely with four factors. Understanding this is essential to budget correctly:
- Part complexity — a one-piece rear wing is simpler than a full rear bumper with cut-outs and channels.
- Number of cavities — multi-cavity moulds raise the investment but lower the cost per unit on large batches.
- Required finish — a carbon texture, fine grain or smooth surface changes the mould preparation time.
- Number of colours or variants — black, carbon texture and grey can use the same mould; an exclusive colour needs extra adjustment.
How the tooling pays for itself: the mould cost is a one-off amount split across the first units of the order. With a large batch, the tooling cost per part becomes negligible and the final price is driven by material and labour. That is why volume is always the variable that most influences the final price.
Lead times in practice
| Stage | Lead time | What happens |
|---|---|---|
| Briefing and scanning | 5 to 10 days | Feasibility confirmation and 3D survey |
| CAD modelling | 7 to 12 days | Definition of line, fixing and thickness |
| Prototype and approval | 10 to 15 days | First physical part and fine-tuning |
| Mould and production | 15 to 25 days | Mould build and series injection |
| Total to shipment | 37 to 62 days | Summing the four stages |
International freight comes afterwards: 25 to 35 days door-to-door by air, or 40 to 55 days by sea, added to the 37 to 62 days of production.
3 mistakes that delay OEM projects most
Mistake 1: Kit scope undefined in the first conversation
Defining the scope over WhatsApp with "I want a full kit for model X" creates back-and-forth. The scope needs to list which parts, which years and the finish level before any modelling starts.
Mistake 2: Not involving the technical team early
The earlier the technical team joins, the cheaper the project. Validating feasibility for a specific model before paying for a mould avoids discovering at the prototype that the part conflicts with the reversing sensor or the number-plate mount.
Mistake 3: Approving the prototype without a fit test
A prototype approved visually may not fit. Insist that the part is tested on the vehicle (or on a dimensional mock-up) before final approval. Ask for installation photos at prototype sign-off.
Frequently asked questions
How much does developing a mould cost?
The cost depends on part complexity, the number of cavities, the finish and the colour variants. It is quoted as a one-off amount, separate from the production price. Request the quote with the kit scope to get the exact figure.
How many days from briefing to shipment?
Between 37 and 62 days of development and production, before freight. Models already in our line skip this stage and ship in 25 to 35 days.
Can I use the same mould for several years of the same model?
It depends on the differences between generations. When the vehicle changes shape at the rear or along the side, the mould no longer works. The technical team confirms this at the scanning stage.
Is the kit plug-and-play even on new models?
Yes. Development uses the real vehicle as the base, and the fixing points follow the originals. No cutting or drilling of the bodywork is needed.
How do I request a quote for a mould project?
By WhatsApp (+86 180 2717 0857) or email (contato@sporttyper.com.br). Tell us the make, model, year or year range, which kit parts you want, the finish required and the estimated production quantity.
Next step
Send the project scope. The technical team replies with feasibility, a schedule and the tooling quote — with no obligation.
Note: the mould development lead times and tooling values in this guide are Ruiton line references and vary with part complexity and the number of cavities. The quote is always confirmed case by case.